Associated Project
Sources of Noise
- Heavy construction equipment.
Utility Shutdowns
- None at this time.
Deliveries
- Rock and Sand.
- Advance Darainage System (ADS) components.
- General construction materials.
Events for upcoming week
- Begin covering Berger Family Lawn (BFL) system with rock.
- Begin Newcomb Quad Excavation
- Continue marking utilities as needed.
- Review site drainage plan.
- Work with Facilities as they make steam line repairs in the area.
- Continue drainage installation on Newcomb quad.
- Air spade utility route areas in coordination with Bayou Tree and design team.
- Remove spoils from site.
- Continue Drainage inlet installations on BFL.
Recap of Week ending May 24, 2025
- Complete BFL base rock and ADS installation.
- Begin ADS rock fill.
- Work with facilities as they investigate what appears to be a steam leak.
- Receive and Lay additional Mats for Newcomb quad drainage system excavation.
- Air spade around drainage boxes and utility routes near trees.
- Install inlat and drain lines for NW BFL drainage.
- Meet to discuss drainage layout along Dixon sidewalk and Newcomb Arts sidewalk (28 May 2026).
- Receive long reach excavator on site.