Unified Green - Week of June 1, 2026

Associated Project

Sources of Noise

  • Heavy construction equipment.

Utility Shutdowns

  • None at this time.

Deliveries 

  • Rock and Sand.
  • Advance Darainage System (ADS) components.
  • General construction materials.

Events for upcoming week

  • Begin covering Berger Family Lawn (BFL) system with rock.
  • Begin Newcomb Quad Excavation
  • Continue marking utilities as needed.
  • Review site drainage plan.
  • Work with Facilities as they make steam line repairs in the area.
  • Continue drainage installation on Newcomb quad.
  • Air spade utility route areas in coordination with Bayou Tree and design team. 
  • Remove spoils from site.
  • Continue Drainage inlet installations on BFL.

Recap of Week ending May 24, 2025

  • Complete BFL base rock and ADS installation.
  • Begin ADS rock fill.
  • Work with facilities as they investigate what appears to be a steam leak.
  • Receive and Lay additional Mats for Newcomb quad drainage system excavation.
  • Air spade around drainage boxes and utility routes near trees.
  • Install inlat and drain lines for NW BFL drainage.
  • Meet to discuss drainage layout along Dixon sidewalk and Newcomb Arts sidewalk (28 May 2026).
  • Receive long reach excavator on site.