Sources of Noise
- Hand Tools.
Utility Shutdowns
- None at this time.
Deliveries
- Materials.
Events for upcoming week
- Begin routing pipes in the CO2 Room.
- Mount manifold to wall.
- Provide power for Cylinder Room fixtures.
- Continue cleaning site.
Recap of week ending September 27, 2024
- Passed State Fire Marshall inspection.
- Generator start up and tested by Kohler Rep and TBES.
- Completed electrical trim out.
- Caulked louvers.
- Fertilized grass.
- Design team created punch list.
- Moved temporary fencing and materials off site.