TNPRC TUTSI Freezer Project - Week of March 14, 2025

Sources of Noise

-None at this time.

Utility Shutdowns

-None at this time.

Deliveries

-None at this time.

Events for upcoming week

-Project Complete.

Recap of week ending March 7, 2025

-Completed additional work including:
-Adding four pressure gauges.
-Provided nitrogen tank.
-Connected nitrogen tank to manifold.
-Tested connections.