TNPRC TUTSI Freezer Project - Week of July 19, 2024

Sources of Noise

  • Hand Tools.
  • Skid Steer.
  • Small generator

Utility Shutdowns

  • None at this time.

Deliveries 

  • Materials.

Events for upcoming week

  • Energize building electrical system.
  • Continue terminating circuits for the sub-panels.
  • Install exhaust fans.
  • Skim and sand drywall.
  • Open Ceiling inspection by the Parish and TBES.

Recap of week ending July 12, 2024

  • Completed Electrical Room rough in. 
  • Passed St. Tammany Parish electrical inspection.
  • Notified Cleco and ready to energize.
  • Installed dehumidifiers in the building.
  • Began taping and floating drywall.
  • Installed conduit for controls to the existing Freezer Building.