TNPRC RBL Lab Renovation - Week of February 14, 2025

Sources of Noise

-Hand Tools.

Utility Shutdowns

-None at this time.

Deliveries

-None at this time.

Events for upcoming week

-Remove existing circuit in sub panel by lab door.
-Pull new circuit with higher amperage to RTU’s.
-Install heating coil at RTU’s.

Recap of week ending February 7, 2024

-Manufacture continued coding the Sequence of Operations program.
-Set point troubleshooting results were unsatisfactory.
-Discussed moving forward with a temporary heating coil.