TNPRC JRH1 - Week of October 9, 2024

Sources of Noise

-Hand tools.
-Welding machine.

Utility Shutdowns

-None at this time.

Deliveries

-None at this time.

Events for upcoming week

-Touch up paint new latches and repairs.
-Weld angle for building tunnels.
-Weld angle around exterior tunnels to close gaps.
-Squeeze chutes in fabrication.
-Aluminum sliding doors being fabricated.
-Complete exterior plumbing trim out.
-Address floor scuffs.


Recap of week ending October 4, 2024

-Poured and finished perimeter concrete walk.
-Finished HDPE tunnel assemblies. 
-Continued welding angle for building tunnels.
-Completed interior latches, barrel locks, and proper gate alignments.
-Aluminum tunnel door mockup approved by Vet Med.
-Finished plumbing trim out in building.