Sources of Noise

  • Hand tools.
  • Welding machines.
  • Concrete trucks

 

Utility Shutdowns

  • None at this time.

 

Deliveries

  • None at this time.

 

Events for upcoming week

  • Pour perimeter concrete walk.
  • Weld angle for building tunnels.
  • Complete HDPE building tunnel assemblies. 
  • Weld angle around exterior tunnels to close gaps.
  • Squeeze chutes are being fabricated.
  • Finish plumbing trim out.


Recap of week ending September 27, 2024

  • Prepped and formed perimeter concrete walk.
  • Started HDPE tunnel assemblies. 
  • Completed exterior tunnel bridges.
  • Resumed welding angle for building tunnels.
  • Plumbing trim out.
  • Installed exterior vestibule panels by each gate.
  • Continued interior latches, barrel locks, and proper gate alignments.
  • Provided aluminum tunnel door mockup.