TNPRC JRH1 - Week of December 13, 2024

Sources of Noise

-Hand tools.
-Welding machine.

Utility Shutdowns

-None at this time.

Deliveries

-None at this time.

Events for upcoming week

-Deliver and install (1) chute.
-Continue exterior enclosure metal roof panels.
-Insulate exterior lixit pipes.
-Finish exterior chain fabric vestibule.
-Install tunnel doors for the exterior enclosures.

Recap of week ending December 6, 2024

-Started installing exterior enclosure metal roofs.
-Sanded and cold galvanized exterior enclosure welds.
-Installed chutes. Only (1) chute remains to install.
-Interior enclosure tunnel doors installed.
-Building to exterior tunnel doors installed.
-Heating system inspected by Commissioning Agent. 
-Began exterior chain vestibule by double doors.