TNPRC JRH1 Phase II - Week of June 9, 2025

Sources of Noise

-Hand tools.
-Welding machines.
-Mini Excavator.
-Skid Steer.

Utility Shutdowns

-None Scheduled.

Deliveries

-Materials and equipment.

Events for the upcoming week

-Mount mockup squeeze chute to the cage for review.
-Critique squeeze chute with Vet Med and design team.
-Pull chain, hang gates, and detail fencing throughout the site.
-Install pre-plumbed hose bibs and lixit drops as cages progress.
-Continue insulation following plumbing drops.
-Finish all cage full welds.
-Continue the tunnel through the building fabrication offsite.

Recap of week ending June 6, 2025

-Received squeeze chute mockup.
-Continued plumbing insulation in building section 1.
-Installed lixit and hose bib pre-plumbed drops.
-Framing erected in all areas.
-Pulled chain fabric, hung gates, and detailed panels throughout the site.