Sources of Noise
-Man lift.
-Skid Steer.
-Small excavator.
-Georgia Buggy.
-Hand tools.
Utility Shutdowns
-None Scheduled.
Deliveries
-Concrete, materials, and equipment.
Events for upcoming week
-Continue interior and exterior cage mockups.
-Begin pulling electrical circuits to the K Field pump equipment.
-Continue plumbing and electrical rough in.
-Pour flush hydrant concrete pads throughout South Campus.
Recap of week ending February 7, 2025
-Began both the interior and exterior cage mockups.
-Applied epoxy to the exterior cage curbs.
-Finished plumbing the lift station pump assembly.
-Completed pouring exterior cage sloped insets.
-Continue plumbing and electrical rough in.
-Duct work complete except for the Vestibule area.
-Poured and finished drainage crickets at cage corners.