TNPRC JRH1 Phase II - Week of December 13, 2024

Sources of Noise

-Lull.
-Man lift.
-Hand tools.

Utility Shutdowns

-None at this time.

Deliveries

-Materials and equipment.

Events for upcoming week

-Overhead MEP rough in.
-Lift HVAC unit to roof.
-Tie Cage Run 26 roof chain fabric.
-Deliver and install (1) prefabricated heater enclosure for Cage Run 26.
-Have Architect approve heater enclosure once installed at Cage Run 26.

Recap of week ending December 6, 2024

-MEP Ongoing.
-Installed Cage Run 26 roof chain fabric.