TNPRC JRH1 Phase II - Week of August 23, 2024

Sources of Noise

  • Excavator.
  • Bobcat.
  • Bore machine.

Utility Shutdowns

  • None at this time.

Deliveries

  • Materials and equipment.

Events for upcoming week

  • Continue installing 8” water main from tunnel to water source.
  • Continue subsurface boring for new gas main.
  • Prep K Field by removing materials, equipment, and tools.


Recap of week ending August 16, 2024

  • Trenched, fused, and buried 8” water main from K Field through tunnel.
  • Final grade re-established through the tunnel.
  • Pre-fused approximately 1,000 LF. of 8” water main stocked in K Field.
  • Bored approximately 1,350 LF. of 2” gas main.