Sources of Noise
-Man lifts.
-Hand tools.
-Welding machines.
Utility Shutdowns
-None Scheduled.
Deliveries
-Materials and equipment.
Events for the upcoming week
-Weld structural framing and pull chain fabric throughout site.
-Fabricate cage gates and install.
-Lift station float requires installation.
-Continue plumbing lixits and hose bibs.
-Install aluminum protection panels at hose bib drops.
-Vet Med site walkthrough to review tunnel installation.
Recap of week ending April 18, 2025
-Pulled main electrical feed.
-Began making up electrical panel to provide permanent power.
-Installed mockup tunnel from the building to the exterior cage.
-Framed exterior enclosures, pulled chain, and hung gates.
-Resumed interior cage framing in building section 2.
-With Vet Meds approval, continued lixit and hose bib drops.