TNPRC Cage Runs 23 and 26-Week of May 23, 2025

Sources of Noise

-Hand Tools.

Utility Shutdowns
-None at this time.

Deliveries

-Materials and equipment.

Events for the upcoming week - R 26 
-Pressure test newly installed gas main, (Stub-up to manifold).
-Continue electrical and controls rough in.

Recap of week ending May 16, 2024 - R 26

-Installed gas manifold.
-Pulled the main electrical feed from the panel to the disconnect.
-Continued electrical and controls rough in. 
-Preconstruction meeting held with CenterPoint Energy.
-Work to commence on Cage Run 23 upon Cage Run 26 completion. 
-Nearby NHP’s to be relocated to Cage Run 26 upon completion