Sources of Noise
-Hand Tools.
Utility Shutdowns
-None at this time.
Deliveries
-Materials and equipment.
Events for the upcoming week - R 26
-Pressure test newly installed gas main, (Stub-up to manifold).
-Continue electrical and controls rough in.
Recap of week ending May 16, 2024 - R 26
-Installed gas manifold.
-Pulled the main electrical feed from the panel to the disconnect.
-Continued electrical and controls rough in.
-Preconstruction meeting held with CenterPoint Energy.
-Work to commence on Cage Run 23 upon Cage Run 26 completion.
-Nearby NHP’s to be relocated to Cage Run 26 upon completion