Sources of Noise
- Hand Tools
Utility Shutdowns
- None currently.
Deliveries
- Materials and equipment.
Events for upcoming week
- Perform ground penetrating survey to prep for crane placement.
- Lift mechanical equipment to roof.
- Tape and float drywall.
- Skim and prep ceiling.
- Continue chilled water and steam lines.
- Electrical rough-in ongoing.
- ACM panel exterior hat channel progressing.
Recap of week ending October 17, 2019
- Began taping and floating drywall. Continued installing Drywall.
- Hat channel installation for Architectural Panels moving forward.
- Crawlspace chilled water and steam line installation ongoing.
- Continued installing Penthouse electrical panels and conduits.
- Duct installation advancing.
- Continued skimming and prepping ceiling.