Sources of Noise
- Hand Tools
Utility Shutdowns
- None at this time.
Deliveries
- Materials and equipment.
Events for upcoming week
- Continue casework MEP connections.
- Install supply and exhaust grilles.
- Hang doors and install hardware.
- Test electrical devices, trim out, pull circuits, and hang new lights.
- Caulk glazing and install rubber seal on exterior glass system.
- Continue applying finishes.
Recap of week ending January 23, 2019
- Demolished AHU3 and duct. Prepped and Poured concrete in penetration.
- Energized new panels and lights, removed temporary electrical service, pulled circuits, provided power to casework, and continued hanging lights.
- Continued interior door and hardware installation.
- Began leveling subfloor and install floor system.
- Drywall and frame finish ongoing.
- Completed courtyard exterior glazing. ACM panels at 90%.
- Casework plumbing tie in. Rerouted existing chill and steam lines.