Sources of Noise

  • Hand tools.

Utility Shutdowns

  • None at this time.

Deliveries 

  • None at this time.

Events for upcoming week

  • Site walkthrough with Design Team and Vet Med to punchout project.
  • Issue punchlist to contractors.

Recap of week ending August 11, 2022

  • Cummins Representative performed the Generator start up process.
  • TBES Commissioned generator, load bank, and electrical system.
  • Modified and re-installed aluminum chute gates.
  • Currently mowing grass throughout site.