RMH - Week of October 9, 2024

Sources of Noise
-Vehicles
-Dumpsters
-Tools/ Equipment

Utility Shutdowns
-None at this time

Deliveries 
-General construction materials. 
-Dumpsters
-Concrete trucks

Events for upcoming week
-Continue South and West exterior landscaping and walkway installation.
-Continue North exterior hardscape.
-Continue interior stairwell finishing and painting.
-Continue interior door installation.
-Continue wooden base board installations all floors.
-Continue Painting where needed on all floors.
-Continue MEP Trim out on floors 1-5 where painted walls are available.
-Continue Generator startup/ test prep.
-Thompson team inspections continue where available.
-Continue interior metal frame and glass installation.
-Continue trim out and testing of Fire alarm devices.
-Continue Fan coil unit testing in closets. Prepare for startups.
-Continue site cleaning. 
-Continue Historic wood restoration and lobby stairway painting. 
-Continue data, access, A/V and CCTV installations where available.
-Continue lobby capital repairs.
-Continue Architect 1st floor review.

Recap of Week ending October 6, 2024

-Continue MEP trim out all floors. Complete stairwell lighting installations.
-Continue Paint and Tape/ Float/ and Finish throughout.
-Install drywall underneath stairwells where available, patch exit sign adjustment areas.
-Continue Interior metal frame and glass installations 2nd, 3rd, and 4th floors.
-Continue Precast stair tread installations and landing adjustments.
-Continue VAV and smoke damper adjustments.
-Continue Fire Alarm trouble shooting and system checks.
-Remove spoils, set forms/ rebar, and pour West exterior walkways and landscaping.
-Continue baseboard installations and historic wood restorations throughout. Begin Lobby stair painting.
-Set ceramic tiles on front porch.
-Remove spoils and continue exterior grading of North and South for landscaping and driveway. Test for north exterior compaction. Passed.
-Begin North Fiber pull from ground box to Richardson Building.
-Set West exterior e-pole foundation with conduits. 
-Continue interior door hardware installations.
-Wire vending room and West entry transfer hinges.
-Continue electric strike opening adjustments.
-Site walk with facilities.