Sources of Noise
- Heavy machinery operations.
- Dumpster activities.
Utility Shutdowns
- None at this time
Deliveries
- Dumpsters
- Construction materials
Events for upcoming week
- Reorganize site. Old Job trailer removal and dumpster relocations.
- Continue interior Hangers and wall layouts moving up the floors.
- Continue electrical installation on interior floors. (Rough in)
- Continue tuckpointing activities West and NE historical facades. Brick repairs as needed.
- Continue Fire lid install 2nd floor existing structure, moving to 3rd floor.
- Continue waterproofing the exterior sheathing.
- Install plumbing and HVAC pipes, ducts, and hangers throughout.
- Continue Historical window installation.
- Hang sprinkler pipe hangers throughout.
- Place SW electrical vault in ground.
- Pour North stairs. Complete North and prepare for south stairs to be poured.
Recap of week ending November 5, 2023
- Continue West elevation tuck pointing activities.
- Finish North flat roof, continue Southeast roof repairs, continue NE flashing install, continue NE slate install.
- Continue plumbing installation throughout building.
- Continue 2nd floor fire lid and wall framing.
- Continue interior electrical rough in (lighting, floor boxes, etc.)
- Continue HVAC duct install and insulation.
- Continue historical window installation.
- Continue install stair 2 (South addition) sections and handrails.
- Place and begin configuring main electrical switchgear. Move SW electrical vault into position. Repair damaged sewer drain near vault.
- Begin Fire alarm cabling.
- Core masonry walls as needed.
- Begin North addition Storefront windows.