RMH - Week of November 10, 2023

Sources of Noise

  • Heavy machinery operations.
  • Dumpster activities.

Utility Shutdowns

  • None at this time

Deliveries 

  • Dumpsters
  • Construction materials

Events for upcoming week

  • Reorganize site. Old Job trailer removal and dumpster relocations.
  • Continue interior Hangers and wall layouts moving up the floors.
  • Continue electrical installation on interior floors. (Rough in)
  • Continue tuckpointing activities West and NE historical facades. Brick repairs as needed.
  • Continue Fire lid install 2nd floor existing structure, moving to 3rd floor.
  • Continue waterproofing the exterior sheathing.
  • Install plumbing and HVAC pipes, ducts, and hangers throughout.
  • Continue Historical window installation.
  • Hang sprinkler pipe hangers throughout.
  • Place SW electrical vault in ground. 
  • Pour North stairs. Complete North and prepare for south stairs to be poured.

Recap of week ending November 5, 2023

  • Continue West elevation tuck pointing activities.
  • Finish North flat roof, continue Southeast roof repairs, continue NE flashing install, continue NE slate install.
  • Continue plumbing installation throughout building.
  • Continue 2nd floor fire lid and wall framing.
  • Continue interior electrical rough in (lighting, floor boxes, etc.) 
  • Continue HVAC duct install and insulation.
  • Continue historical window installation.
  • Continue install stair 2 (South addition) sections and handrails. 
  • Place and begin configuring main electrical switchgear. Move SW electrical vault into position. Repair damaged sewer drain near vault.
  • Begin Fire alarm cabling.
  • Core masonry walls as needed.
  • Begin North addition Storefront windows.