Sources of Noise
-Vehicles
-Dumpsters
-Tools/ Equipment
Utility Shutdowns
-None at this time.
Deliveries
-General construction materials.
-Dumpsters.
Events for upcoming week
-*Observe Quiet Week*
-Continue Interior punch list activities.
-Continue historic wood finishing and painting.
-Continue touch up Painting on all floors and stairwells.
-Continue MEP adjustments as required.
-Thompson team commissioning activities continue where available.
-Continue site cleaning/ reconfiguring.
-Site Visit with Advancement Team.
-Site Visit with Tulane Access Control team.
-Install lobby foyer capitals.
-Continue 1st floor West elevation window sealing.
Recap of Week ending December 8, 2024
-Continue Paint and touch up throughout.
-Continue historic wood restorations, painting, and staining in 2nd floor lobby and stair 6 and stair 7.
-Continue Punch list corrective actions.
-Adjust steam line heat exchanger.
-Continue Quality Control activities.
-Continue Card Access installations.
-Continue exterior site cleanup.
-Paint metal stair rails in stair 1 and 2.
-Forbo floor cleaning information session.
-Five Star Vending room survey.
-Install E-pole emergency phone, camera, and light. Pending power up when network is connected.