Sources of Noise
- Vehicles
- Dumpsters
- Tools/ Equipment
Utility Shutdowns
- None at this time
Deliveries
- General construction materials.
- Dumpsters
Events for upcoming week
- Continue East and Northwest exterior drainage installation and repair.
- Continue wooden base board installations throughout.
- Continue VCT installation in 301. Continue carpet installation in 304, prep 404.
- Continue 5th floor, stair 4, and stair 5 ceiling Tape, Float, and Finish. Homasote board installation continues 4th floor. Paint/ caulk installed Homasote.
- Continue MEP Trim out on floors 1-4 where painted walls are available.
- Continue Roof flashing and brick work adjustments.
- Thompson team inspections continue where available.
- Continue interior metal storefront installations. Add glass wherever framing it ready.
- Continue topping slab at interstitial floors.
- Install FDC (point of connection at the fire pump room).
- Prepare front porch for waterproofing.
- Continue preparations on front porch for surfacing.
- Continue Fan coil unit testing in classrooms. Prepare for startups.
- Continue stair 4 and 5 handrail installations.
Recap of Week ending August 18, 2024
- Move East Fence out to encompass parking spaces along West Road 17Aug2024.
- Dismantle North load platform scaffolding. Begin removing materials from site.
- Continue MEP installations throughout.
- Continue Tape/ Float/ Finish as walls and ceilings become available.
- Continue duct insulation and fan coil unit wiring/ testing.
- Add blocking for Zinsell doors.
- Fire alarm trim out continues throughout.
- Begin removing paint from historic door frames.
- Dig Southeast ext for Trench drain.
- Install Loyola gate reader conduit to J-box at South exterior.
- Complete VCT installation in room 302, begin room 301.
- Install partitions in 2nd floor restrooms, layout 3rd floor Women’s room.
- Caulk and paint interior windows.