Richardson Memorial - Week of October 7,2022

Sources of Noise

  • Heavy Equipment operations
  • Auger cast engine, pumps, and drilling
  • Hand tools (Hammer drills, etc.)

Utility Shutdowns

  • None at this time

Deliveries 

  • 30yd dumpsters being swapped as needed to remove debris
  • General construction materials (supplies, lumber, ets)
  • Additional scaffolding

Events for upcoming week

  • Continue Auger Cast delivery, assembly, and positioning
  • Begin Auger cast drilling
  • Prepare for Steam Condensate Shut down to allow pipe capping and demo
  • Complete 1st Fl ext window abatement
  • Address east lighting timing
  • 1st Fl N demo and debris clearing
  • Continue safety improvements for tour groups and workers
  • Tulane School of Architecture tour – 10/12 @ noon

Recap of week ending Oct 5, 2022

  • Excavator delivery for Auger cast activity
  • Complete NE beam pocket drilling and bolt base plates
  • S and SE ext, begin 1st fl ext window abatement and priming
  • 1N interior floor abatement
  • 1N and Central MEP and wall/ ceiling demo
  • East Light pole base demo
  • Begin upper-level floor repairs (add plywood to problem spots)
  • Conducted two Arch department faculty/ staff tours 10/4 and 10/5
  • Lay mats in NE ext of building and add fencing to segment site