Richardson Memorial - Week of October 21, 2022

Sources of Noise

  • Heavy Equipment operations
  • Auger cast engine, pumps, and drilling
  • Vehicle movement

Utility Shutdowns

  • None at this time

Deliveries 

  • 30yd dumpsters being swapped as needed to remove debris
  • General construction materials (supplies, lumber, etc.)
  • Grout trucks for Piles

Events for upcoming week

  • Continue pile drilling and grout pouring in SE Site area
  • Testing 5th floor dormer structural integrity
  • Continue cleanup and residual demo
  • Complete interior window priming
  • Demo Fire pump room
  • Continue safety improvements
  • Tulane School of Architecture tour – 10/26 @ noon

Recap of week ending Oct 19, 2022

  • Complete Auger Cast assembly and begin pile drilling
  • Demo remaining MEP 1st Floor including steam room
  • Remove debris and detail clean interior.
  • Complete South Stair Demo
  • Complete interior window abatement. Continue priming window frames
  • Demo central walls and remaining ceilings 1st Fl
  • Demo residual items throughout the building.
  • Demo North concrete and lay down Limestone
  • Continued Safety improvements with additional areas sectioned off