Richardson Memorial - Week of October 14,2022

Sources of Noise

  • Heavy Equipment operations
  • Auger cast engine, pumps, and drilling
  • Hand tools (Hammer drills, etc.)

Utility Shutdowns

  • None at this time

Deliveries 

  • 30yd dumpsters being swapped as needed to remove debris
  • General construction materials (supplies, lumber, etc.)

Events for upcoming week

  • Complete Auger Cast assembly and walk unit to South East site area
  • Begin Auger cast drilling
  • Demo Steam Condensate pipe and pumping equipment inside RMH
  • Complete interior window priming
  • Clear interior debris
  • Complete South Stair Demo
  • Layout saw cutting for 1st Fl slab infrastructure paths
  • Continue safety improvements
  • Tulane School of Architecture tour – 10/19 @ noon

Recap of week ending Oct 12, 2022

  • Complete Auger Cast delivery and begin assembly
  • Complete Steam condensate line cap
  • Install timer for West Road lighting
  • Begin South Interior Stair Demo, including landing
  • Complete interior window frame abatement. Prime interior frames
  • Demo North walls and remove debris 1st Fl
  • Demo 4th Fl Classroom. Walls, Ceiling, MEP
  • Conducted Arch department faculty/ staff tours 10/12
  • Continued Safety improvements with additional areas sectioned off