Richardson Memorial - Week of November 4,2022

Sources of Noise

  • Heavy Equipment operations
  • Auger cast engine, pumps, and drilling
  • Vehicle movement

Utility Shutdowns

  • None at this time

Deliveries 

  • Construction dumpsters
  • General construction materials (supplies, lumber, etc.)
  • Grout trucks for Piles

Events for upcoming week

  • Move Ramp and hose from Gibson hydrant to the Richardson Building hydrant and place ramp on sidewalk near the bike racks.
  • Begin pile drilling and grout pouring in NE Site area
  • Continue testing structural integrity
  • Abate North interior stair
  • Continue Safety improvements
  • Remove excess dirt from SE site

Recap of week ending Oct 26, 2022

  • Completes Drill and cast SE pilings
  • Sweep West Road
  • Complete build out of South stair scaffold
  • Conducted Architecture tour 10/26
  • Walk auger rig to NE Site
  • Begin Structural assessment of North Dormers on 4th Fl