Richardson Memorial - Week of June 10, 2025

Sources of Noise
-N/A

Utility Shutdowns
-None at this time.

Deliveries 
-N/A

Events for upcoming week
-Warranty period monitoring.
-S&S to finish surfacing of 1st floor center stair risers and post bases.
-Laser cutter exhaust for units 3 and four to be installed.
-Test Laser cutter exhaust shut down.
-Thompson team to Test and Balance adjusted HVAC units.
-Energy management system meter monitoring to have communications verified.
-Verify last card reader entries with Gene and Marilyn.


Recap of Week ending June 8, 2025

-Review issues logs.
-Checked Main electrical room meter connections and verify communications.
-Conducted Heat exchange training with Entra and Gaudin… Thompson team recorded session.
-Replace thermafuser blades on 3, 4a, and 4b.
-Generator control unit replaced.