Sources of Noise

  • Heavy Equipment operations
  • Vehicle movement
  • Dumpster activities (deliveries, dumping, compacting, etc)

Utility Shutdowns

  • None at this time

Deliveries 

  • General construction materials (supplies, lumber, etc.)
  • Dumpsters.

Events for upcoming week

  • Install water, sewer, drainage lines along N to NE Ext.
  • Install new Sewer Man hole NE ext.
  • Install joists to 2S where plywood was lifted to 2nd floor.
  • Continue Selective Demo 2N floor joist and decking.
  • Continue Install/ repair 2N and 2 Central floor joist and decking.
  • Reorganize N ext for Utilities work along East property line toward. 
  • Richardson Building NE corner.

Recap of week ending Feb 12, 2023

  • Load supplies to 2nd floor.
  • Debris removal.
  • Install new sewer and water lines along N ext.
  • Construct man hole @ NW ext.
  • Back fill to cover new installation of man hole, sewer, and water pipe.
  • Demo 2N floor decking and joists as required.
  • Repair joists and decking above 1st fl planning room.
  • Receive steam line for upcoming install.