Paul Hall Clean Room - Week of January 12, 2026

Sources of Noise

  • General Construction activities.

Utility Shutdowns

  • None at this time.

Deliveries 

  • General construction materials.

Events for upcoming week

  • Continue MEP installations.
  • Continue Site cleaning.
  • Continue installing plenums partition walls.
  • Monitor Cut station between Boggs and Flower Hall.


Recap of Week ending January 11, 2026

  • Data head end configuration.
  • Add top rails and wall posts. Begin Panel installations.
  • Remove Items from Paul Hall Lobby.
  • Reset lobby furniture.
  • Continue electrical and plumbing connections to the plenums.
  • Complete plenum coil connections.
  • Continue Cleaning and checking for metal shavings from installations.