Sources of Noise
- General Construction activities.
Utility Shutdowns
- None at this time.
Deliveries
- General construction materials.
Events for upcoming week
- Continue MEP installations.
- Continue Site cleaning.
- Continue installing plenums partition walls.
- Monitor Cut station between Boggs and Flower Hall.
Recap of Week ending January 11, 2026
- Data head end configuration.
- Add top rails and wall posts. Begin Panel installations.
- Remove Items from Paul Hall Lobby.
- Reset lobby furniture.
- Continue electrical and plumbing connections to the plenums.
- Complete plenum coil connections.
- Continue Cleaning and checking for metal shavings from installations.