Nursing Aron L4 Renovation - Week of June 1, 2026

Sources of Noise

  • N/A


Utility Shutdown

  • N/A

Deliveries

  • N/A

Events for upcoming week

  • Furniture delivery  
  • AV and low voltage device install continued
  • Punch list/fieldwire issues addressed for all trades
  • Carpet install in main corridor  

Recap of work performed (5/26/26 – 5/29/26)

  • Door delivery and install
  • Furniture delivery 
  • AV and low voltage device install
  • Paint touch up and punch list items addressed
  • General cleaning