Nursing Aron L4 Renovation - Week of January 12, 2026

Sources of Noise

  • Power tools: grinders, Hammer drills, chipping guns, etc...

Utility Shutdown

  • N/A

Deliveries

  • Air Handler Units 1/12/26 and 1/13/26

Events for upcoming week

  • Acoustic ceiling grid install
  • Air handle units delivery and install
  • Door frame install and welded    
  • Wire pulled for panels and lighting
  • Float, tape, finish, 1st coat walls
  • Begin of floor prep


Recap of work performed (1/05/26 – 1/09/26)

  • Door frame install
  • Close wall and framing thru-out all phases
  • Floating and taping, priming and 1st coat thru-out all phases
  • Classroom partition wall top rail installed  
  • Mechanical rooms prep for AHU arrival
  • Access control wire hung