TNPRC JRH1 - Week of February 14, 2025

Sources of Noise

-Hand tools.

Utility Shutdowns

-None scheduled.

Deliveries 
-Materials.

Events for upcoming week

-Weld additional latches on exterior cages as per Vet Med’s request.
-Punch out walk-through scheduled Wednesday.
-Wash down cages, floors, and walls.
-Finalize grading.

Recap of week ending February 7, 2025

-Applied final coat of paint on doors and frames.
-Finalized door hardware.
-Cleaned tools, equipment, and swept the Vestibule Area.
-Punched lock holes in HDPE sliding chute doors.