Weinmann Roof Repair - Week of August 23, 2024

Sources of Noise

  • Angle grinders and hand tools

Utility Shutdowns:

  • None

Deliveries

  • None

Events for upcoming week

  • Move scaffolding from Monroe side to Freret side of building
  • Build scaffolding at the main entrance to support the swing stage
  • Penthouse apron detail work
  • Sealing and PMMA work in Mechanical Yard 2
  • Sealing and PMMA work in Mechanical Yard 5


Recap of work performed (Aug 13 - 19, 2024)

  • Top layer of roofing material (white cap) on center tower complete
  • North wall sealed, gutter work complete
  • Gutter work on north wall
  • Sealant and PMMA work in Mechanical Yard 2