TNPRC JRH1 - Week of October 13, 2023

Sources of Noise

  • Hand Tools.
  • Lull.
  • Welding machine.

Utility Shutdowns

  • None at this time.

Deliveries 

  • None at this time.

Events for upcoming week

  • Chute mock-up delivered.
  • Program newly routed Data into the TNPRC system.
  • Verify powder coating with Vet Med.
  • Begin addressing conflicts discovered in walk through.


Recap of week ending October 6, 2023

  • Completed hanging Data wire from ā€œSā€ Building to JRH1.
  • Began cleaning site adjacent to the exterior enclosure construction.
  • Resumed generator hook up.
  • Site walk with Architect and Vet Med.