Sources of Noise
- Heavy Equipment
- Demolition
- Utility Vehicles
- Power Tools
Utility Shutdowns:
- Deliveries
- Job trailers
- Misc jobsite materials
- Misc equipment
- Concrete Trucks
Events for upcoming week
- Continue install of Stair 1
- Continue exterior sheathing
- Continue fireproofing 5th floor
- Start steel tie in @ Flower Hall
- Continue mechanical & electrical rough in
- Continue work on Chilled Water & Steam
- Continue framing walls on 3rd & 4th floor
Recap of week performed (September 18th – September 24th 2022)
- Continued fireproofing on 5th floor
- Continued overhead rough-in on 2nd, 3rd & 4th floor
- Continued work on Chilled Water & Steam @ S side
- Continued framing walls on 2nd & 3rd floor