TNPRC Breeding Colony Expansion - Week of March 25, 2022

Sources of Noise

  • Excavation equipment.
  • Hand tools.

Utility Shutdowns

  • None at this time.

Deliveries 

  • Materials and equipment.

Events for upcoming week

  • Continue installing gates.
  • Begin installing corrugated roof panels.
  • Set fabricated chutes for both enclosures.
  • Hydroseed newly graded and disturbed areas.
  • Install roof sprinklers.
  • Mount swivels.

Recap of week ending March 24, 2022

  • CLECO installed electrical meter.
  • Project electrician energized circuits.
  • Completed perch and swivel installation.  
  • Began setting animal chutes.