Paul Hall - Week of June 11, 2021

Sources of Noise

  • None

Utility Shutdowns:

  • None

Deliveries

  • None

Events for upcoming week

  • Broadmoor will continue to perform cost estimating services. 
  • Site review of demolition enabling will continue. 
  • Enabling bids are scheduled to be provided to Tulane this week. 
  • Contract document review will continue at OAC meetings. 

Recap of week performed (June 06 – June 12, 2021)

  • Review of Tulane’s 50% DD review comments is ongoing. 
  • Paul Hall OAC meeting occurred on 06/08/2021. 
  • Tulane and Broadmoor performed multiple site walks in preparation of the enabling bid cost estimate and schedule. 
  • Arrow fencing met on site to review future site fencing needs. 
  • Bayou Trees met on site to review future sidewalk installation and tree pruning requirements.