Sources of Noise
- Hand tools and power tools
- Work vehicles
- Selective Demolition
- Material Deliveries
Utility Shutdowns:
- None at this time
Deliveries
- Delivery of drywall will occur on 10/02
Events for upcoming week
- The contractor will continue MEP layout and installation.
- Selective demolition will occur as needed.
- Framing will continue.
Recap of week performed (Sept 27 – Oct 03, 2020)
- HTE completed a new wire feed tie-in. The electrical contractor continues to rough-in electrical branch circuitry.
- MCC continues duct work fabrication and installation. Plumbing layout and installation continues.
- Donahue Favret is constructing a lift station in the empty elevator shaft.
- Framing layout and framing installation have commenced.
- Selective demolition continues.