Sources of Noise
- Hand tools and power tools
- Work vehicles
- Selective Demolition
- Material Deliveries
Utility Shutdowns:
- None scheduled at this time
Deliveries
- Delivery of mechanical equipment scheduled to occur this Saturday, 9/19.
Events for upcoming week
- The contractor will continue MEP layout and installation.
- Selective demolition will occur as needed.
- Framing will continue.
Recap of week performed (Sept 13 – Sept 19, 2020)
- Layout and installation of electrical systems continues.
- HTE is schedule to perform a multi-floor wire pull on 9/19.
- MCC continues duct work fabrication and installation.
- Donahue Favret sealed the exterior penetrations.
- Framing layout and selective framing installation have commenced.