Newcomb Hall Renovation First and Fourth Floors - Week of June 1, 2026

 

Sources of Noise

  • Heavy Equipment
  • Demolition
  • Power Tools

Utility Shutdowns:

  • None

Deliveries

  • Misc jobsite materials
  • Misc equipment
  • Concrete Trucks

Events for upcoming week

  • Continue New elevator install  
  • Prepping for transformer start up
  • Layout & prep for lightning protection plan
  • Continue installing steel @ old elevator shaft
  • Continue stairwell fire door work
  • Continue sprinkler riser rough in
  • Continue misc MEP rough in  
  • Continue work on 2nd & 3rd floor
  • Continue DOAS hook up
  • Continue misc plaster repairs 
     

Recap of week performed ( May 25th- May 30th  2026)

  • Existing elevator demo complete
  • Begin installing new elevator
  • Continued stairwell openings for new fire doors
  • Installing new elevator steel
  • Continued misc plaster repairs
  • Continued tape, float & prime 1st floor
  • Continued misc MEP rough in