Associated Project
Sources of Noise
- Selective Demolition
- Power Tools
Deliveries
- Misc jobsite materials
Events for upcoming week
- Basement move out & clean
- 1st floor clean & prep for punch
- 2nd floor restroom clean & punch
- Continue mecho shade install
- Continue misc plaster work
- Continue misc Commissioning
- Continue 4th floor FAZR ceiling
- Continue 4th floor millwork install
- Complete floating floor @ 4th floor
- Continue misc doors & hardware
- Complete millwork install @ elevator landings
- Complete concrete refinishing @ 1st floor
- Continue 1st floor paint
- Continue FAZR install
- Installing roof tiles @ central roof gable
Recap of week performed (September 20-26)
- 4th floor Mechoshade install
- Misc Commissioning ongoing
- Continued installing doors & hardware throughout
- Continued concrete refinishing on 1st floor
- Continued millwork @ 1st floor
- Started 4th floor millwork
- Continued installing floating floor @ 4th floor
- Continued glazing @ 4th floor aluminum storefront
- Layout & prep for handrail install