Newcomb Hall First and Fourth Floor Renovation - Week of September 28, 2026

Sources of Noise

  • Selective Demolition
  • Power Tools

Deliveries

  • Misc jobsite materials

Events for upcoming week

  • Basement move out & clean
  • 1st floor clean & prep for punch
  • 2nd floor restroom clean & punch
  • Continue mecho shade install  
  • Continue misc plaster work
  • Continue misc Commissioning  
  • Continue 4th floor FAZR ceiling
  • Continue 4th floor millwork install
  • Complete floating floor @ 4th floor
  • Continue misc doors & hardware  
  • Complete millwork install @ elevator landings
  • Complete concrete refinishing @ 1st floor
  • Continue 1st floor paint
  • Continue FAZR install  
  • Installing roof tiles @ central roof gable

Recap of week performed (September 20-26)

  • 4th floor Mechoshade install  
  • Misc Commissioning ongoing
  • Continued installing doors & hardware throughout
  • Continued concrete refinishing on 1st floor  
  • Continued millwork @ 1st floor
  • Started 4th floor millwork  
  • Continued installing floating floor @ 4th floor  
  • Continued glazing @ 4th floor aluminum storefront
  • Layout & prep for handrail install