Newcomb Hall First and Fourth Floor Renovation - Week of September 21, 2026

Sources of Noise

  • Heavy Equipment
  • Demolition
  • Power Tools
     

Deliveries

  • Misc jobsite materials
  • Concrete Trucks

Events for upcoming week

  • Continue raised seating platform on 4th floor
  • Start glazing 4th floor storefront
  • Start 4th floor millwork install
  • Complete floating floor @ 4th floor
  • Installing doors & hardware 
  • Complete millwork install @ elevator landings
  • Complete concrete refinishing @ 1st floor
  • Continue 1st floor paint
  • Continue FAZR install 
  • Continue mechoshade install @ 4th floor
  • Installing roof tiles @ central roof gable


Recap of week performed (September 13-19)

  • Continued installing doors & hardware throughout
  • Continued concrete refinishing on 1st floor 
  • Completed restroom partitions @ 1st & 2nd floor
  • Completed carpet tile install @ 1st floor
  • Continued millwork install @ 1st floor
  • Prepping for millwork install on 4th floor
  • Continued glazing @ 4th floor storefront
  • Continued installing floating floor @ 4th floor