Sources of Noise
- Heavy Equipment
- Demolition
- Power Tools
Deliveries
- Misc jobsite materials
- Concrete Trucks
Events for upcoming week
- Continue raised seating platform on 4th floor
- Start glazing 4th floor storefront
- Start 4th floor millwork install
- Complete floating floor @ 4th floor
- Installing doors & hardware
- Complete millwork install @ elevator landings
- Complete concrete refinishing @ 1st floor
- Continue 1st floor paint
- Continue FAZR install
- Continue mechoshade install @ 4th floor
- Installing roof tiles @ central roof gable
Recap of week performed (September 13-19)
- Continued installing doors & hardware throughout
- Continued concrete refinishing on 1st floor
- Completed restroom partitions @ 1st & 2nd floor
- Completed carpet tile install @ 1st floor
- Continued millwork install @ 1st floor
- Prepping for millwork install on 4th floor
- Continued glazing @ 4th floor storefront
- Continued installing floating floor @ 4th floor