Associated Project
Sources of Noise
- Heavy Equipment
- Demolition
- Power Tools
Deliveries
- Misc jobsite materials
- Concrete Trucks
Events for upcoming week
- Start 4th floor millwork install
- Continue installing floating floor @ 4th floor
- Installing doors & hardware
- Continue millwork install @ elevator landings
- Continue concrete refinishing @ 1st floor
- Continue 1st floor paint
- Continue FAZR install
- Continue mechoshade install @ 4th floor
- Installing roof tiles @ central roof gable
Recap of week performed (September 6-12)
- Started installing doors & hardware throughout
- Continued concrete refinishing on 1st floor
- Installing restroom partitions @ 1st & 2nd floor
- Carpet tile install @ 1st floor
- Contnued millwork install @ 1st & 4th floor
- Continued glazing @ 4th floor storefront
- Continued installing floating floor @ 4th floor