Sources of Noise

  • Heavy Equipment
  • Demolition
  • Power Tools

Utility Shutdowns:

  • None

Deliveries

  • Misc jobsite materials
  • Misc equipment
  • Concrete Trucks  

Events for upcoming week

  • Continue misc plaster repairs
  • Continue DOAS rough in  

Recap of week performed (April 26-May 2)

  • Demo 1st floor slab @ elevator shaft
  • Continued electrical rough in @ 1st floor wainscot
  • Continued tape, float, prime 1st floor walls
  • Continued floor box rough in on 1st floor
  • Continued DOAS install & rough in  
  • Continued misc 4th floor framing