Newcomb Hall 1st and 4th Floor Renovation - Week of March 6, 2026

Sources of Noise 

  • Heavy Equipment
  • Demolition
  • Power Tools

 

Utility Shutdowns: 

  • None

 

Deliveries 

  • Misc jobsite materials
  • Misc equipment
  • Concrete Trucks

 

Events for upcoming week 

  • Continue work @ duct chases
  • Continue sheetrock install on 1st floor
  • Continue 1st Floor electrical & plumbing rough in
  • Continue layout & install of misc MEP
  • Continue basement MEP re-route work
  • In wall inspections
  • Installing wall insulation/begin closing walls

 

Recap of week performed (February 22-28, 2026) 

  • Temporary restroom trailer delivered & set
  • Installing sheetrock on 1 side of 1st floor walls
  • Continued  HVAC controls rough in on 1st floor
  • Continued sprinkler install on 1st floor
  • Continued MEP re-route work in basement
  • Continued duct insulation on 1st floor
  • Continued electrical rough in on 1st floor
  • Fireproofing 4th floor beams & columns