Sources of Noise
- Heavy Equipment
- Demolition
- Power Tools
Utility Shutdowns:
- None
Deliveries
- Misc jobsite materials
- Misc equipment
- Concrete Trucks
Events for upcoming week
- Continue work @ duct chases
- Continue sheetrock install on 1st floor
- Continue 1st Floor electrical & plumbing rough in
- Continue layout & install of misc MEP
- Continue basement MEP re-route work
- In wall inspections
- Installing wall insulation/begin closing walls
Recap of week performed (February 22-28, 2026)
- Temporary restroom trailer delivered & set
- Installing sheetrock on 1 side of 1st floor walls
- Continued HVAC controls rough in on 1st floor
- Continued sprinkler install on 1st floor
- Continued MEP re-route work in basement
- Continued duct insulation on 1st floor
- Continued electrical rough in on 1st floor
- Fireproofing 4th floor beams & columns