Sources of Noise
- Heavy Equipment
- Demolition
- Power Tools
Utility Shutdowns
- None
Deliveries
- Misc jobsite materials
- Misc equipment
- Concrete Trucks
Events for upcoming week
- Form & pour transformer pad
- Start sprinkler rough in on 1st floor
- Continue 1st Floor electrical rough in
- Continue work @ light monitors
- Continue layout & install of misc MEP
- Continue layout & framing of 1st floor walls
- Continue basement MEP re-route work
Recap of week performed ( January 18th- January 24th 2026)
- Continued duct reroute work in basement
- Continued rough in @ basement electrical tie in
- Continued layout & install of duct on 1st floor
- Continued steel work @ light monitors