Sources of Noise

  • Heavy Equipment
  • Demolition
  • Power Tools

 

Utility Shutdowns

  • None

 

Deliveries

  • Misc jobsite materials
  • Misc equipment
  • Concrete Trucks

 

Events for upcoming week

  • Form & pour transformer pad  
  • Start sprinkler rough in on 1st floor
  • Continue 1st Floor electrical rough in
  • Continue work @ light monitors
  • Continue layout & install of misc MEP
  • Continue layout & framing of 1st floor walls
  • Continue basement MEP re-route work

 

Recap of week performed ( January 18th- January 24th   2026)

  • Continued duct reroute work in basement
  • Continued rough in @ basement electrical tie in
  • Continued layout & install of duct on 1st floor
  • Continued steel work @ light monitors