Mussafer Hall - Week of March 11, 2018
Sources of Noise
- Delivery Trucks
- Heavy Equipment
- Power Tools
Utility Shutdowns
- Future electrical shut down to repair temp power pole to involve Alcee Fortier. To be Determined
Deliveries
- Metal Panels, Roof Material, Windows, Lumber, Equipment
- Door Hardware
Events for upcoming week
- Contractor to continue installing Storefront
- Sheetrock install at addition to continue
- Work @ bay windows to wrap up
- Roof work to continue
- Contractor to continue duct insulation @ VAVs
- Stucco & plaster work to continue
- A/C to be powered up – 100% fresh air
- High Voltage work to wrap up
Recap of week ending (March 10, 2018)
- Contractor began stucco on E side
- Storefront install began @ 2nd & 3rd floor E side
- Sheetrock install @ penthouse completed
- Contractor completed work @ Stair 1 & landing
- Contractor completed sewer tie in
- Waterproofing continues
- High voltage testing conti0
- Contractor continued work @ final Bay Windows
- Contractor continued sheetrock at 2nd floor of addition
- Duct insulation continues @ New addition