Sources of Noise
-Heavy Equipment
-Dump trucks
Utility Shutdowns
-None at this time.
Deliveries
-Construction equipment.
-Sand/ gravel
-General construction materials
Events for upcoming week
-Pave base layer of Engineering Road from Freret Street to Paul Hall dock.
-Make preparations to allow coordinated deliveries with SSE.
-Continue surface demo and excavation for drainage lines and detention area.
-Remove Spoils.
Recap of Week ending February 9, 2025
-Back fill and compact area above 1st detention area.
-Configure temp circuit for lighting circuit as solutions explored.
-Repour grout to repair disintegrated duct bank concrete. E.P. Breaux verified the circuit wasn’t damaged and recommended the repair.
-Passed compression test for next section of backfill.
-Pour and form curbing to Paul Hall dock.
-Pour areas around manhole covers and cleanouts.