College Track LaSalle Garage - Week of March 13, 2026

Sources of Noise

  • Power tools: grinders, Hammer drills, chipping guns, etc...


Utility Shutdowns

  • None


Deliveries

  • None

 

Events for the upcoming work week

  • ENFRA roughing in mechanical rm on the roof
  • Marvins dropping lights in grid on the first floor and Mezz as needed
  • CPC painting as needed
  • CSI Insulating throughout space as needed
  • King installing drywall and framing as needed
  • WT Enterprise replacing handrails in stairwells 
     

Recap of work performed (March2-6, 2026)

  • Enfra working on roughing in mechanical room on the roof
  • Marvin installing panels and starting to drop in 2’x4’lights in ceiling grid on the mezz
  • King finished up outside overhang and framing ceilings on the mezz
  • CPC taping and floating and installing final paint as needed in areas that are finished
  • Jefferson sprinkler had a scheduled shutdown to tie the 2 existing systems together
  • WT enterprise started replacing handrails in the stairwells
  • De George glass replaced broken glass on the Mezz