Sources of Noise
- Power tools: grinders, Hammer drills, chipping guns, etc...
Utility Shutdowns
- None
Deliveries
- None
Events for the upcoming work week
- ENFRA roughing in mechanical rm on the roof
- Marvins dropping lights in grid on the first floor and Mezz as needed
- CPC painting as needed
- CSI Insulating throughout space as needed
- King installing drywall and framing as needed
- WT Enterprise replacing handrails in stairwells
Recap of work performed (March2-6, 2026)
- Enfra working on roughing in mechanical room on the roof
- Marvin installing panels and starting to drop in 2’x4’lights in ceiling grid on the mezz
- King finished up outside overhang and framing ceilings on the mezz
- CPC taping and floating and installing final paint as needed in areas that are finished
- Jefferson sprinkler had a scheduled shutdown to tie the 2 existing systems together
- WT enterprise started replacing handrails in the stairwells
- De George glass replaced broken glass on the Mezz