Wilson Athletic Center Renovation - Week of June 18, 2021

Sources of Noise

  • Power hand tools.

Utility Shutdowns

  • None at this time. 

Deliveries 

  • Materials.

Events for upcoming week

  • Continue ceiling grid.
  • Installing ceiling lighting conduits.
  • Adjust sprinkler heads.
  • Install drywall at the knee wall.
  • Apply final paint to ceiling and walls.
  • Install HVAC grilles.

Recap of week ending June 17, 2021

  • Completed Atrium electrical circuit relocation.
  • Began routing ceiling lighting conduits.
  • Landed circuits in electrical panel.
  • Ceiling grid installation is ongoing.
  • Completed additional ceiling deck skimming.
  • Continued applying paint to ceiling and exposed conduits.