Sources of Noise
- Power hand tools.
Utility Shutdowns
- None at this time.
Deliveries
- Materials.
Events for upcoming week
- Continue ceiling grid.
- Installing ceiling lighting conduits.
- Adjust sprinkler heads.
- Install drywall at the knee wall.
- Apply final paint to ceiling and walls.
- Install HVAC grilles.
Recap of week ending June 17, 2021
- Completed Atrium electrical circuit relocation.
- Began routing ceiling lighting conduits.
- Landed circuits in electrical panel.
- Ceiling grid installation is ongoing.
- Completed additional ceiling deck skimming.
- Continued applying paint to ceiling and exposed conduits.