Sources of Noise
- Hand Tools
Utility Shutdowns
- None currently.
Deliveries
- Materials and equipment.
Events for upcoming week
- Complete wall MEP rough-in and begin hanging drywall.
- Begin installing roof chilled water lines.
- Continue domestic water and vent tie in.
- Ceiling mock-up ongoing.
- Apply spray foam insulation to exterior walls.
- Continue routing circuits from electrical panels to Penthouse
Recap of week ending September 19, 2019
- Passed the partial open wall inspection.
- Started grinding ceiling for mock-up.
- Began routing conduits from electrical panels to penthouse.
- Continued hanging VAV boxes, dampers, and ducts.
- Insulating pipes, domestic water tie in and floor cores ongoing.